隧道方案高速公路隧道进洞专项施工方案.docx
- 文档编号:7532189
- 上传时间:2023-01-24
- 格式:DOCX
- 页数:20
- 大小:31.34KB
隧道方案高速公路隧道进洞专项施工方案.docx
《隧道方案高速公路隧道进洞专项施工方案.docx》由会员分享,可在线阅读,更多相关《隧道方案高速公路隧道进洞专项施工方案.docx(20页珍藏版)》请在冰豆网上搜索。
隧道方案高速公路隧道进洞专项施工方案
【隧道方案】高速公路隧道进洞专项施工方案
目
录
一、编制依据............................................................1二、编制原则..............................................................1三、工程地质概况..........................................................1四、施工方案..............................................................2
(1)测量放线.........................................................................................................................2
(2)洞顶截水沟施作.............................................................................................................3(3)边仰坡开挖.....................................................................................................................3(4)边仰坡防护.....................................................................................................................4①边仰坡防护施工方法...................................................................................................4②水泥砂浆锚杆施工方法...............................................................................................4③C20喷射混凝土施工方法...........................................................................................5④钢筋网的施工方法.......................................................................................................5(5)套拱、大管棚施作.........................................................................................................61、管棚设计参数.............................................................................................................62、施工准备.....................................................................................................................63、施工方法.....................................................................................................................6A、套拱施工............................................................................................................6B、搭设钻机施工作业平台:
................................................................................7C、钻进作业............................................................................................................7D、扫孔....................................................................................................................8E、下管....................................................................................................................8F、注浆....................................................................................................................9G、施工过程技术措施..........................................................................................10(6)明洞开挖.......................................................................................................................10(7)明洞衬砌施作...............................................................................................................111、仰拱施工...................................................................................................................112、明洞洞身衬砌施工...................................................................................................113、明洞回填施工...........................................................................................................114、明洞衬砌施工要求...................................................................................................12(8)洞口段超前小导管支护...............................................................................................121、超前小导管注浆施工...............................................................................................12A、施工方法..........................................................................................................12B、施工工艺流程..................................................................................................13D、小导管施工要求...............................................................................................13五.监控量测措施..........................................................141、监测点布置.......................................................................................................................142、监测数据的处理及反馈...................................................................................................143、监控量测频率及测点增减调整.......................................................................................15六.安全质量保证措施......................................................161、组织保证措施...................................................................................................................162、思想保证措施...................................................................................................................163、管理措施...........................................................................................................................16
4、技术保证措施...................................................................................................................175、其他安全保证措施...........................................................................................................186、施工安全应急预案...........................................................................................................19A、应急预案的目的.......................................................................................................19B、应急预案方针和原则...............................................................................................19C、应急预案组织机构和职责.......................................................................................19①应急指挥中心成员组成.....................................................................................19②应急指挥中心职责.............................................................................................19③通讯联络组职责.................................................................................................20④应急抢险组职责.................................................................................................20⑤技术保障、安全保障组.....................................................................................20⑥后勤救护组职责.................................................................................................21D、应急物资配备..........................................................................................................23E、应急响应程序流程..................................................................................................23F、应急事故处理..........................................................................................................25G、应急恢复和关闭......................................................................................................25七.施工环保、水土保持、文明施工措施......................................251、环境保护措施...................................................................................................................252、水土保持措施...................................................................................................................263、文明施工措施...................................................................................................................26八.施工资配置..........................................................271、主要施工人员配置...........................................................................................................272、主要施工机械设备配置...................................................................................................27九.附图..................................................................28
白龙山隧道进洞施工方案
一、编制依据1、毕节至都格高速公路BD-T15合同段施工招标文件。
2、毕节至都格高速公路BD-T15合同段《两阶段施工图设计》。
3、《公路工程技术标准》(JTGB01-2021)。
4、《公路隧道施工技术规范》(JTJ024-2021)。
二、编制原则1、优先考虑施工安全、质量、环保。
精心组织施工,合理安排工序,确保无安全、质量、环境事故发生。
2、在施工方案中,坚持施工技术先进、施工方案可行、重信誉守合同、施工组织科学合理、按期优质安全高效、不留后患。
3、现场施工的实际情况。
三、工程地质概况
白龙山隧道位于六盘水市水城县玉舍乡,为分离式隧道全长4025m,最大埋深328m。
我标段为白龙山隧道后半段,都格段出口洞门型式为端墙式,右线起讫桩号K202+650-K204+675,全长2025m,出口段为曲线R-900,纵坡为-1.54%;左线起讫桩号ZK202+590-ZK204+600,全长2021m,出口段为曲线R-960,纵坡为-1.54%;隧道出口段,埋深14-53m,洞内加强支护,右线管棚长为28m,左线管棚长为40m,洞口边仰坡采用挂网锚喷防护。
白龙山隧道出口覆盖层为破残积碎石土层,岩体破碎,围岩为中风化灰岩,。
岩体呈碎裂状结构,透水性强,属较弱岩。
围岩无自稳能力,易坍塌,仰坡岩土稳定性差,易向下滑塌。
四、施工方案进洞按“先排水、再进洞,统筹安排,减少干扰”的原则进行。
隧道开工前对洞口位置及安全进洞现场研究确定,做好洞口范围的排水,边仰坡率可视实际开挖稳定情况酌情调整,在能保证边仰坡稳定的情况下,以尽量少挖为原则,严禁洞口大开挖、大刷坡,防止滑坡及坍塌,以策安全进洞。
隧道进洞施工顺序为:
测量放线—洞口截水沟开挖及砼浇筑—边坡清顺—边仰坡防护—套拱、大管棚施作—明洞开挖—明洞衬砌施作—洞口段超前小导管支护工艺流程图
(
(1)测量放线开工前已完成导线、水准点的复测和加密工作,并申报驻地办和总监办。
测量组首先对进洞的各个桩点进行复核并测设边仰坡开口线及隧道中线和开挖断面,放出截水沟位置以及洞口各部尺寸。
洞口开挖
边、仰坡防护
洞口排水系
洞口施工工艺流程图洞门施工
洞口段衬砌施工≮020米
管棚、明洞施工
(
(2)
)
洞顶截水沟施作拟定施工顺序:
测量放样、边沟开挖、夯实平整沟底、沟底铺砌、沟身砌筑。
洞顶截水沟采用M7.5浆砌片石施作,置于开挖线外侧5米。
截水沟采用人工开挖,局部石方采用风镐或钢钎凿除。
根据地形气候等情况,截水沟应及时安排在边仰坡开挖前进行。
当开挖至设计深度时,应将沟槽基底夯拍平顺,整齐,无倒坡。
沟底铺筑5cm厚的砂砾垫层,沟底、沟身采用M7.5号浆砌片石砌筑,沟底预留2~3cm厚用高标砂浆抹平,确保沟平顺,沟身勾缝为凹缝。
洞顶截水一般每隔壁10~15m设置一道伸缩缝,缝宽2cm,缝内填沥青防水材料。
施工基本要求:
a、砌体砂浆采用重量的比用称计量以确保配合比的准确性,砌缝内砂浆均匀饱满,勾缝密实。
b、浆砌片(块)石、砼预制块的质量和规格应符合设计要求。
c、基底缩缝应与沟身缩缝对齐。
d、截水沟砌筑采用座浆挤浆法施工,沟底沟身砌筑要求挂线施工,抹面应平整、压光、直顺,不得有裂缝、空鼓现象。
((3)边仰坡开挖白龙山隧道为我标段的控制性工程,出口为俄脚互通起点,该段路基设计为两级边坡的深挖路基,挖方长度325米,挖方总量20万方。
为了保证隧道工程提前进洞,首先考虑将隧道口前进方向80米路基开挖至设计标高。
路基边坡开挖一级防护一级,并在路基左右两侧设置排水沟,将隧道口积水引至路基排水沟,在排水沟端头各设一个集水井,再由高扬程水泵排出天然沟壑。
然后组织足够的机械人员采用24小时两班倒的制度,在一个月内将剩余挖方及防排水工程全
部完成,从而保证隧道工程的排水及运输通道的畅通。
1、准备工作:
a、施工前由测量组对洞口土石方开挖原地貌进行复测,根据复测结果放出洞口边、仰坡开挖边线及开挖高度,并做好测量放样红桩。
b、测量放样范围内的树木、杂草等砍除,清除洞顶山坡上的危石,排除险情。
c、施工前,人员、机械、材料要组织到位,为施工做好准备。
2、为了保证土方开挖采用挖掘机开挖,装载机装碴,机械无法开挖时采用人工开挖,自卸汽车运输至指定弃碴场。
开挖自上而下进行。
接近坡面50cm时坡面采用人工修整,防止机械开挖时产生超挖。
坡率采用坡度尺进行控制,开挖过程中测量组随时检查开挖标高和坡率。
3、表层软石用挖掘机开挖,硬质石方采用电动空压机供风,风钻打眼,松动爆破;爆破作业时严格控制炮眼部位、朝向及炮眼深度和每次爆破的总装药量,同时做好防护措施;接近坡面时采用光面爆破开挖,以减少对边坡的扰动。
((4)边仰坡防护开挖完成后修整边坡清理危石后,应按设计及时施作边仰坡防护工程。
为保证明洞开挖临时边仰坡稳定,边仰坡采用挂网喷砼防护。
支护参数为:
采用4.0m长砂浆锚杆,梅花形布置,间距1.2m*1.2m;挂网采用φ6.5钢筋网,网格间距20cm*20cm;喷射混凝土厚10cm。
①边仰坡防护施工方法拟定施工顺序:
清理边坡、钻孔、清孔、放入锚杆、加压(0.5-1.0Mpa)注浆、挂网、喷砼。
②水泥砂浆锚杆施工方法水泥砂浆配合比(质量比)为:
水泥:
砂:
水=1:
(1~1.5):
(0.45~
0.5),砂的粒径不宜大于3mm。
砂浆应随拌随用,一次拌和的砂浆应在初凝前用完。
注浆孔口压力不得大于0.4MPa。
锚杆杆体用Ф22的Ⅱ级螺纹钢筋制作。
清理边坡完成后,在坡面上按设计要求放样出锚杆的钻孔位置(锚杆间距120__120cm,呈梅花状布置),再用凿岩机械钻孔,成孔后将注浆管插至距孔底5-10cm处,随水泥砂浆的注入缓慢均匀拔出,随即迅速将制作好的杆体插入,插入的杆体不得短于设计长度的95%。
若孔口无砂浆流出,应将杆体拔出重新注浆。
待锚固剂终凝后安设孔口垫板,使锚杆垫板与坡面贴紧
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 隧道 方案 高速公路 进洞 专项 施工